September 16, 2026

Supports the case against policy VA

Virginia federal lawmakers pile on data center bills as Fauquier plans key vote

Sen. Mark Warner and Rep. Suhas Subramanyam rolled out a slate of federal bills including the Data Center Fair Share Act, which would push states to adopt tariffs so data centers cover their own energy infrastructure or forfeit federal highway funds. The push comes as Fauquier County's Planning Commission is set to review the 900 MW, 2.2 million square foot Remington Innovation Campus on September 17.

Virginia Mercury Who pays for the grid buildout Laws, bills and regulation Who holds the risk

Check it: Whether the bills have Republican co-sponsors and any Senate committee movement, and whether the highway-funds enforcement mechanism is likely to survive legislative markup.

September 15, 2026

Supports the case against local OH

Lima, Ohio council passes unanimous 18-month data center moratorium

Lima City Council approved an 18-month moratorium on new data center construction and on new city water requests from outside municipalities, so that staff can study siting, water and power standards. Mayor Sharetta Smith cited Ohio's rapid data center growth. The moratorium does not affect the existing water agreement for a Google data center under development in American Township.

LimaOhio.com Local opposition and consent Water use Siting, zoning and standards

Check it: Whether the pause covers new applications only or freezes projects already in the pipeline, and how the Google American Township carve-out is worded.

Supports the case against local CA

San Francisco supervisors introduce 45-day data center moratorium

Supervisor Shamann Walton, joined by Connie Chan, Chyanne Chen and Jackie Fielder, introduced a 45-day urgency ordinance to freeze new data center approvals, with an eye toward a permanent citywide ban. Under state law the interim ordinance needs a four-fifths vote and can be extended to nearly two years if the planning commission finds a public-welfare threat. The proposal follows expansion plans at NOVVA's 400 Paul Avenue project in Bayview.

Hoodline Local opposition and consent Siting, zoning and standards Air quality and on-site power

Check it: Whether the four-fifths supermajority is secured for the interim ordinance and how the moratorium treats projects that already have entitlements.

Supports the case against local CA

Hayward City Council directs staff to draft data center ban

The Hayward City Council took up a legislative referral from Mayor Mark Salinas and two colleagues directing staff to begin amending the zoning code to prohibit new data centers, following pushback against an approved 76.6-megawatt facility with 28 diesel backup generators. Hayward had already amended its code in April 2026 to require major conditional use permits for such projects.

City of Hayward Local opposition and consent Air quality and on-site power Siting, zoning and standards

Check it: Whether the referral produces an actual ordinance and how it treats data centers that already hold permits, including the 76.6 MW project.

Supports the case against local VA

Loudoun County supervisors advance 12-month pause on new data center applications

In a 7-1-1 vote, the Loudoun County Board of Supervisors directed staff to draft a resolution pausing new data center applications for up to 12 months while it develops new rules. Board Chair Phyllis Randall framed the pause as temporary; the county attorney said an indefinite moratorium would likely be illegal. A final vote is expected in October.

Data Center Dynamics Siting, zoning and standards Local opposition and consent Laws, bills and regulation

Check it: Whether the final October vote adopts the 12-month pause, whether by-right grandfathering is preserved, and how many pending applications would be captured.

Supports the case against legal VA

Virginia DEQ orders Microsoft to pay about $2.5 million over Leesburg generator emissions

Virginia's Department of Environmental Quality issued a consent order requiring Microsoft to pay roughly $2.5 million over air-quality violations at its Compass Creek Parkway data center in Leesburg during a June 27 to July 1, 2025 substation outage. The agency says the site exceeded permitted limits for nitrogen oxides, particulate matter and volatile organic compounds; Microsoft says it has invested about $31 million in reliability upgrades. The order is subject to public comment through October 14.

NewsBreak / WJLA Air quality and on-site power Local opposition and consent Who holds the risk

Check it: Whether this is the largest DEQ air-quality penalty on record, whether the consent order becomes final after public comment, and how backup generator runtime rules apply during grid outages.

September 14, 2026

Supports the case against policy TX

Abbott orders Texas Water Development Board to penalize data centers that skip water-use surveys

Governor Greg Abbott directed the Texas Water Development Board to use its enforcement authority against data centers and other large users that fail to file the state's mandatory water-use survey. The order refers uncooperative operators for possible criminal prosecution and directs the TCEQ to block related permit renewals, with an enforcement report due to the governor by October 14.

Texas Tribune Water use Secret contracts and disclosure Laws, bills and regulation

Check it: Whether any operator has actually been penalized versus put on notice, and how much of the missing data is from data centers specifically as opposed to other large water users.

Supports the case against local OH

Pioneer, Ohio village council imposes six-month data center moratorium

Pioneer village council voted 6-0 to impose a six-month moratorium on data center approvals after a developer approached the planning commission the prior week. The measure blocks the council from acting on any proposed data center during the pause but does not permanently prohibit them and can be shortened by later council action.

Bryan Times Local opposition and consent Siting, zoning and standards

Check it: Whether the developer that prompted the pause has publicly named a site or capacity, and whether the six-month clock could be extended.

Supports the case for company

Cornelis Networks raises $205 million and launches Active Compute Fabric with Qualcomm

Cornelis Networks announced a $205 million funding round led by IAG Capital Partners and unveiled Active Compute Fabric, an AI networking architecture aimed at improving GPU utilization inside and between servers. The company also disclosed a partnership with Qualcomm, part of a broader industry push to reduce idle AI accelerator time.

SiliconANGLE Efficiency and forecasts AI race and national security

Check it: Whether the utilization gains are measured in production workloads or vendor benchmarks, and whether the fabric ships in customer data centers before the end of 2026.

Supports the case for policy OK

Public Service Company of Oklahoma tells regulators data centers can lower bills

PSO went before the Oklahoma Corporation Commission seeking approval for hundreds of millions of dollars in new generation, arguing that data center load will spread fixed costs and reduce residential bills over time. The utility pointed to sister company Indiana Michigan Power, which has asked Indiana regulators for a roughly $100 per year residential reduction tied to large-load growth.

Oklahoma Energy Today Who pays for the grid buildout Jobs Local property tax revenue

Check it: Whether PSO's modeled bill savings assume full contracted load and firm cost recovery from data centers, and how the commission staff and consumer advocate score the claim.